Building Safety Regulator Reform - A 'Fast Track' Process

D
Devonshires

Contributor

Devonshires logo

Based in the City of London for over 150 years, Devonshires is a leading practice providing high-quality, accessible and value-for-money services to domestic and international clients, including developers, local authorities, housing associations and financial services firms. The practice focuses on building strong, long-lasting relationships in order to achieve outstanding results based on practical advice. The foundation of its success is its commitment to people, both its own and those working for its clients. The firm ensures its staff have access to high-quality training and fosters ‘one to one’ connections between its solicitors and clients.

The firm acts on a broad range of matters including projects, property and real estate, securitisation, construction, housing management, commercial litigation, employment, banking, corporate work, and governance. The practice is a leader in social housing, including working on many development projects nationwide and helping to draft legislation.

HRB building control approval applications under the new approval process, known as Gateway 2, have been facing criticism for the significant delays which have a knock on effect to construction projects.
United Kingdom Real Estate and Construction

HRB building control approval applications under the new approval process, known as Gateway 2, have been facing criticism for the significant delays which have a knock on effect to construction projects.

Under the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, the time periods for approval of building control approval applications are 12 weeks for new HRBs and 8 weeks for works to existing HRBs. However, in practice, applications are taking in excess of 30 weeks.

This delay is reportedly due to a combination of the lack of capacity in the Building Safety Regulator's ("BSR") outsourced multi-disciplinary teams ("MDT") and the poor quality, or lack of information, in the applications. It has been reported that it can take up to a month just to appoint an MDT which, in of itself, if pushing applications of the prescribed timelines.

In an attempt to unblock the Gateway process, the Ministry of Housing, Communities and Local Government has announced today that a new 'fast track' process will be introduced in order to support the delivery of the 1.5 million new homes promised by the Government.

To achieve this, and address the outsourcing issue, building inspector and engineering capability is intended to be brought in-house so that the BSR can directly process and review applications. There will be an addition of 100 new BSR team members as part of this 'Plan for Change'.

Former London Fire Brigade commissioner, Andy Roe, will also be chairing the newly established board within MHCLG that will be taking over the functions of the BSR from the HSE in the near future. This board will act as a 'shadow board' until it has been established as an Executive Agency and is one of the 'early steps towards establishing a single construction regulator' - which was one of the key recommendations coming out of the Grenfell Phase 2 report.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See More Popular Content From

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More