With approximately 1,000 lawyers across 17 offices, Seyfarth Shaw LLP provides advisory, litigation, and transactional legal services to clients worldwide. Our high-caliber legal representation and advanced delivery capabilities allow us to take on our clients’ unique challenges and opportunities-no matter the scale or complexity. Whether navigating complex litigation, negotiating transformational deals, or advising on cross-border projects, our attorneys achieve exceptional legal outcomes. Our drive for excellence leads us to seek out better ways to work with our clients and each other. We have been first-to-market on many legal service delivery innovations-and we continue to break new ground with our clients every day. This long history of excellence and innovation has created a culture with a sense of purpose and belonging for all. In turn, our culture drives our commitment to the growth of our clients, the diversity of our people, and the resilience of our workforce.
By April 18, 2026, New York construction litigation will operate on a faster—and far less forgiving—timeline.
United States Real Estate and Construction
Meghan A. Douris’s articles from Seyfarth Shaw LLP are most popular:
  • within Real Estate and Construction topic(s)
  • in South America
  • in South America
  • with readers working within the Advertising & Public Relations, Property and Construction & Engineering industries
Seyfarth Shaw LLP are most popular:
  • within Compliance and Consumer Protection topic(s)

By April 18, 2026, New York construction litigation will operate on a faster—and far less forgiving—timeline. The Avoiding Vexatious Overuse of Impleading to Delay (the "AVOID Act"), signed into law on December 19, 2025, fundamentally rewrites third‑party practice under CPLR § 1007 by imposing strict deadlines to bring subcontractors, suppliers, and other responsible parties into a case.

For owners, developers, general contractors, and their in‑house counsel, this change will shift risk assessment, contract enforcement, and litigation strategy to the very front end of a claim—particularly in New York Labor Law and construction defect cases.

What Changed—and Why It Matters to Construction Cases

Historically, New York defendants could implead subcontractors and other players well into discovery. The AVOID Act ends that practice.

Under the amended CPLR § 1007:

  • Contract‑based indemnity claims must generally be brought within 60 days after the defendant serves its answer.
  • Non‑contractual claims (e.g., contribution or common‑law indemnity) must be asserted within 60 days of "becoming aware" that another party may be responsible.
  • Subsequent layers of third‑party practice are subject to even shorter deadlines (45, 30, and then 20 days).
  • No impleader is permitted after the filing of a Note of Issue, and late third‑party actions must be severed or dismissed and may not be re‑consolidated with the main action.

In construction litigation—where multiple trades, layered contracts, and overlapping insurance programs are the norm—these deadlines dramatically compress the window for action, and companies can no longer wait for discovery to unfold to identify other potential parties.

Owners and contractors will need to:

  • Identify all potentially responsible subcontractors and vendors immediately upon receipt of a complaint.
  • Analyze indemnification, additional insured, and defense provisions before filing an answer.
  • Make early determinations about whether contractual or common‑law rights support impleader.

Failure to act quickly may result in permanent loss of indemnity and contribution claims in the same action, forcing parties to pursue separate lawsuits—often without the leverage or efficiency that joint discovery and trial once provided.

Increased Motion Practice—and New Pressure on Early Investigation

While the statute is framed as an anti‑delay measure, there is concern that it will generate new forms of litigation activity.

The Act's "becoming aware" standard—triggering the 60‑day clock for non‑contractual claims—will almost certainly become a battleground. Expect disputes over:

  • Whether RFIs, contracts, accident reports, or site logs should have triggered awareness;
  • Whether prior tenders or insurance correspondence constituted notice;
  • Whether early investigative steps were "reasonable" under project‑specific circumstances.

For project teams this means earlier site investigations, faster incident reconstruction, and closer coordination between legal, safety, and project management teams than ever before.

Strategic Impacts on Labor Law and High‑Exposure Claims

The AVOID Act may have its largest impact in New York Labor Law §§ 200, 240(1), and 241(6) cases, where defendants routinely rely on aggressive third‑party practice to shift liability downstream.

Because the Act limits impleader timing—but not plaintiffs' ability to control the case—it may:

  • Increase settlement leverage for plaintiffs, who can time the Note of Issue to cut off third‑party claims;
  • Push defendants toward earlier global resolution, before indemnity rights are forfeited;
  • Force owners and contractors to rely more heavily on insurance tender and coverage litigation, rather than third‑party contribution claims in the underlying action.

Practical Takeaways for In‑House Counsel and Executives

The AVOID Act is not just a procedural tweak—it is a business risk issue. Companies operating in New York should consider:

  1. Updating incident‑response playbooks to ensure legal review begins immediately after any serious accident.
  2. Re‑evaluating contract management systems so indemnity and insurance provisions can be identified within days, not months.
  3. Training project teams to flag potential third‑party exposure early, before litigation deadlines close.
  4. Adjusting reserve strategies, recognizing that missed impleader deadlines may shift costs permanently onto the prime defendant.

The Bottom Line

The era of leisurely, discovery‑driven third‑party practice in New York is over. New York's AVOID Act forces construction defendants to act early—investigating promptly, litigating decisively, and locking in risk‑transfer strategies at the outset of a case. For prepared defendants, the result may be leaner, more efficient litigation. For everyone else, delay now carries a steep price: the permanent loss of critical claims.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

[View Source]
See More Popular Content From

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More